![]() |
Press Releases: |
| Project Status: | August 2008 - Currently underway. In
process of manning up. August 2007 - NEW INFORMATION KCP&L & Kiewit Industries tells us the initial hire for a small crew will be Fall / Winter 2007. Increased manpower will come in Spring / Summer 2008. On site now: ECA performing duct bank work - manpower is at approximately 10 - 12 men. RF Fisher putting in temporary power - manpower is at approximately 10 - 15 men. Staco has a small crew doing data com work. May 2007
February 2007
October 2006 - Project is still on schedule. Chimney stack has been awarded to Bordner Technical Services out of Pennsylvania. Work on stack should start 10/16/06. Still looking at man-up starting late March 2007. September 2006 - Four contracts have been let: 1) Kissick Construction will be performing site work including pilings and chimney/stack foundation. Capital Electric is doing some minor associated work for Kissick when needed. 2) Pullman Power was award the chimney/stack award. It will be built under the National Stack and Chimney agreement addendum of the NMA. Bronder Technical Services out of Pennsylvania will be doing the electrical on the stack. They are an IBEW contractor and plan to utilize LU 124 manpower. It will be a small crew of 1 to 4 men with possible 3 shifts on 5 days. Work scheduled to start on October 16th. It is a slip form stack. 3) Liston Clark to perform dirt work on parking lots and lay down yards starting very soon. 4) Inner Fab will be the “go to” contractor on site to perform undefined work that may have been left out of initial planning. July 2006 - Let this fall will be the
electrical packages including some underground, power, parking lot
lighting and site camp and office construction projects. |
Phone (816) 942-7500 Copyright ©2006 IBEW Local 124 - Kansas City, MO