LaCygne Powerhouse
Second shutdown is underway. Kiewit manned up & portions of the work Enerfab has on project have been pushed back to October

bulb

Cerner Project
JE Dunn is general on project. Job not expected to man up until late Summer & is slated to be built in portions working on two buildings at a time.

bulb

R F Fisher
Populos job on 4800 Main just starting. JE Dunn is the general on project. Shawnee Mission hospital utilities job also underway. Not expected to hire for project.

bulb

KCPD East Patrol Crime Lab
Project is ongoing. A number of contractors onsite including Mark One, City Wide, Fisher, Lynch & Lantel. Job is mostly manned up & has a September completion date.

bulb

R/S Electric
Has ongoing work at Harley Davidson, Kelloggs, Ceva Pharmaceuticals & Bayer. Lake City Ammunition plant job should hire this Spring. Expected to hire 20-30.

bulb

Certainteed
Job is ongoing. Both ECA & Superior on project.

bulb

Burns and McDonald
Shaw is working on the project. Not expected to man up until Spring.

bulb

Nearman Power House
Upgrades at Nearman powerhouse in Kansas City, KS has begun. Not expected to man up until late Summer/Fall.

bulb

Iatan Powerhouse

59 day outage scheduled for March 1st & ECA has been awarded project.

bulb

DST
This job is ongoing. P1 is on the project.

bulb

STACO

Jackson County Courthouse is underway. Most likely, will not be hiring for project.

bulb

MARK ONE

Challenger Job located on west outer road north of Tiffany Springs. Manufacture floor panels. Phase one near completion, phase 2 expected to ramp up in March.

Kauffman Stadium WIFI Upgrade. Adding additional digital antenna systems to facilities. Project is expected to hire 30 wiremen.